[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108509,783,1,"单选题","某住宅楼由六个单元组成，其基础工程施工时，拟分成三段组织流水施工，土方开挖总量为9600m3，选用两台挖土机进行施工，采用一班作业，两台挖掘机的台班产量定额均为100m3，则流水节拍应为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","48",false,{"key":16,"text":17,"correct":14},"B","32",{"key":19,"text":20,"correct":21},"C","16",true,{"key":23,"text":24,"correct":14},"D","8","考点:流水施工参数。根据流水节拍定额计算法的公式，t=Q\u002F（S×R×N），即：流水节拍=每个工作段的工作量\u002F（产量定额×台班数×工作班次）=（9600\u002F3）\u002F（100×2×1）=16天。参见教材P25",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]