[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108508":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108508,783,1,"单选题","下列对于固定节拍流水施工描述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","所有施工过程在各个施工段上的流水节拍均相等",true,{"key":16,"text":17,"correct":18},"B","相邻施工过程的流水步距不等",false,{"key":20,"text":21,"correct":18},"C","专业工作队数大于施工过程数",{"key":23,"text":24,"correct":18},"D","施工段之间可以有空闲时间","考点:固定节拍流水施工。在有节奏流水施工中，各施工过程的流水节拍都相等的流水施工，也称为固定节拍流水施工或全等节拍流水施工。特点：（1）所有施工过程在各个施工段上的流水节拍均相等；（2）相邻施工过程的流水步距相等，且等于流水节拍；（3）专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务；（4）各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。参见教材P26。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]