[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108506,783,1,"单选题","某五层现浇钢筋混凝土建筑结构的施工，其主体工程由支模板、绑扎钢筋和浇筑混凝土3个施工过程组成，每个施工过程在施工段上的延续时间均为5天，划分为3个施工段，则总工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","25",false,{"key":16,"text":17,"correct":14},"B","40",{"key":19,"text":20,"correct":21},"C","85",true,{"key":23,"text":24,"correct":14},"D","100","考点:固定节拍流水施工。按固定节拍流水施工工期计算公式：T=（m+n－1）t+∑G+∑Z－∑C=（5×3+3－1）×5=85（天）。题中是五层现浇钢筋混凝土建筑结构的施工，等于施工段加倍。参见教材P27",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]