[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108505,783,1,"单选题","某工程有5个施工过程，划分为3个施工段组织固定节拍流水施工，流水节拍为2天，施工过程之间的组织间歇合计为4天。该工程的流水施工工期是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","18",true,{"key":20,"text":21,"correct":14},"C","20",{"key":23,"text":24,"correct":14},"D","26","考点:固定节拍流水施工。（3+5-1）×2+4=18（天）。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]