[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108504,783,1,"单选题","某建设工程划分为3个施工过程，4个施工段组织加快的成倍节拍流水施工，流水节拍分别为6天、3天、9天和12天，则需要专业工作队总数为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","10",true,{"key":23,"text":24,"correct":14},"D","11","考点:成倍节拍流水施工。成倍节拍流水施工计算专业工作队数，首先需要求出流水步距，K=最大公约数{6，3，9，12}=3（天）；专业工作队数=6\u002F3+3\u002F3+9\u002F3+12\u002F3=10。参见教材P30。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]