[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108503,783,1,"单选题","某建筑物基础工程的施工过程、施工段划分和流水节拍（天）见下表。如果组织非节奏流水施工，则基础二浇筑完工时间为第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9",true,{"key":16,"text":17,"correct":18},"B","11",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","15","考点:流水步距的确定。开挖和浇筑流水步距=3，所以基础二浇筑完工时间=3+（4+2）=9（天）。参见教材P31",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]