[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108502,783,1,"单选题","下列关于非节奏流水施工的特点，说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","相邻施工过程的流水步距不尽相等",false,{"key":16,"text":17,"correct":14},"B","专业工作队数等于施工过程数",{"key":19,"text":20,"correct":21},"C","各施工过程在各施工段的流水节拍全不相等",true,{"key":23,"text":24,"correct":14},"D","有的施工段之间可能有空闲时间","考点:非节奏流水施工的特点。选项C应为各施工过程在各施工段的流水节拍不全相等。参见教材P31",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]