[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108501,783,1,"单选题","某工程有3个施工过程，流水步距分别为2、5，其中第一个施工过程持续时间为8天，第二个施工过程持续时间为11天，第三个施工过程持续总时间是9天，第二与第三施工过程有3天的搭接，则流水施工工期为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","13",true,{"key":20,"text":21,"correct":14},"C","18",{"key":23,"text":24,"correct":14},"D","19","考点:流水施工工期的确定。经计算可知，计算流水施工工期=2+5+9-3=13（天）。参见教材P32",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]