[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108499,783,1,"单选题","建设工程组织流水施工时，相邻专业工作队之间的流水步距不尽相等，但专业工作队数等于施工过程数的流水施工方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定节拍流水施工和加快的成倍节拍流水施工",false,{"key":16,"text":17,"correct":14},"B","加快的成倍节拍流水施工和非节奏流水施工",{"key":19,"text":20,"correct":14},"C","固定节拍流水施工和一般的成倍节拍流水施工",{"key":22,"text":23,"correct":24},"D","一般的成倍节拍流水施工和非节奏流水施工",true,"考点:有非节奏流水施工的特点。一般的成倍节拍流水施工和非节奏流水施工相邻专业工作队之间的流水步距不尽相等，但专业工作队数等于施工过程数。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]