[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108498":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108498,783,1,"单选题","某分部工程由4个施工过程组成，分为3个施工段组织流水施工，其流水节拍（天）见下表。则流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":14},"C","22",{"key":22,"text":23,"correct":24},"D","23",true,"考点:流水施工工期的确定。用错位相减取大差法计算流水步距， 在差数列中取最大值求出流水步距。 施工过程Ⅰ与Ⅱ之间的流水步距：K1,2=3天；施工过程Ⅱ与Ⅲ之间的流水步距：K2,3=5天；施工过程Ⅲ与Ⅳ之间的流水步距：K3,4=4天。流水施工工期=（3+5+4）+（3+4+4）=23天。参见教材P32",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]