[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108497,783,1,"单选题","某工程划分为三个施工过程、4个施工段组织流水施工，流水节拍见下表，则该工程流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":14},"C","26",{"key":22,"text":23,"correct":24},"D","27",true,"考点:流水施工工期的确定。施工过程Ⅰ：4，9，12，16；施工过程Ⅱ：3，5，8，10；施工过程Ⅲ：4，7，12，16。KⅠ，Ⅱ=max{4，6，7，8，-10}=8（天）；KⅡ，Ⅲ=max{3，1，1，-2，-16}=3（天）。T=（8+3）+16=27（天）。参见教材P32",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]