[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108496,783,1,"单选题","某分部工程划分为2个施工过程、3个施工段组织流水施工，流水节拍分别为5天、3天、4天和2天、4天、3天，则流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","15",true,"考点:流水施工工期的确定。累加数列错位相减取大差法计算流水步距K＝6，流水工期＝6＋（2＋4＋3）＝15天。参见教材P32。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]