[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108495,783,1,"单选题","某工程组织非节奏流水施工，两个施工过程在4个施工段上的流水节拍分别为5、8、4、4天和7、2、5、3天，则该工程的流水施工工期是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","25",true,{"key":23,"text":24,"correct":14},"D","28","考点:流水施工工期的确定。累加数列：5、13、17、21；7、9、14、17；流水步距：8；流水工期=8+17=25（天）。参见教材P33。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]