[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108491":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108491,783,1,"单选题","流水施工中最常见的施工方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","非节奏流水施工",true,{"key":16,"text":17,"correct":18},"B","有节奏流水施工",false,{"key":20,"text":21,"correct":18},"C","等步距异节奏流水施工",{"key":23,"text":24,"correct":18},"D","异步距异节奏流水施工","考点:流水施工的基本组织方式。非节奏流水施工是指在组织流水施工时，全部或部分施工过程在各个施工段上的流水节拍不相等的流水施工。这种施工是流水施工中最常见的一种。参见教材P26",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]