[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108489,783,1,"单选题","如果根据工期要求采用倒排进度的方法确定流水节拍，则下列描述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可反算出所需要的工人数或机械台班数",false,{"key":16,"text":17,"correct":14},"B","必须检查劳动力供应的可能性",{"key":19,"text":20,"correct":21},"C","无需考虑工作面是否足够",true,{"key":23,"text":24,"correct":14},"D","必须检查材料和施工机械供应的可能性","考点:流水施工参数。如果根据工期要求采用倒排进度的方法确定流水节拍时，可反算出所需要的工人数或机械台班数。但在此时，必须检查劳动力、材料和施工机械供应的可能性，以及工作面是否足够等。参见教材P25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]