[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108487,783,1,"单选题","下列计算式中，对流水节拍的计算错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流水节拍=工程量×计划时间定额\u002F（计划产量定额×人数×工作班次）",true,{"key":16,"text":17,"correct":18},"B","流水节拍=工程量×计划时间定额\u002F（人数×工作班次）",false,{"key":20,"text":21,"correct":18},"C","流水节拍=施工段需要的劳动量\u002F（人数×工作班次）",{"key":23,"text":24,"correct":18},"D","流水节拍=工程量\u002F（计划产量定额×人数×工作班次）","考点:流水施工参数。流水节拍=工程量\u002F（计划产量定额×人数×工作班次）=工程量×计划时间定额\u002F（人数×工作班次）=施工段需要的劳动量\u002F（人数×工作班次）。参见教材P25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]