[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108484,783,1,"单选题","某基础工程土方开挖总量为2000立方米，该工程拟分4个施工段组织固定节拍流水施工，两台挖掘机的台班定额均为50立方米\u002F台班，其流水节拍应为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","4","考点:流水施工参数。根据流水节拍定额计算法的公式，t＝Q\u002F（S×R×N），即：流水节拍＝每个工作段的工作量\u002F（产量定额×台班数×工作班次）＝（2000\u002F4）\u002F（50×2×1）＝5天。参见教材P25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]