[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108483,783,1,"单选题","建设工程组织非节奏流水施工时，计算流水步距时第一步是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","取最大值",false,{"key":16,"text":17,"correct":14},"B","错位相减",{"key":19,"text":20,"correct":21},"C","累加数列",true,{"key":23,"text":24,"correct":14},"D","求最大公约数","考点:流水步距的确定。在非节奏流水施工中，通常采用累加数列错位相减取大差法计算流水步距。由于这种方法是由潘特考夫斯基首先提出的，故又称为潘特考夫斯基法。这种方法简捷、准确，便于掌握。累加数列错位相减取大差法的基本步骤如下：（1）对每一个施工过程在各施工段上的流水节拍依次累加，求得各施工过程流水节拍的累加数列；（2）将相邻施工过程流水节拍累加数列中的后者错后一位，相减后求得一个差数列；（3）在差数列中取最大值，即为这两个相邻施工过程的流水步距。参见教材P31",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]