[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108481,783,1,"单选题","某分部工程有两个施工过程，各分为4个施工段组织流水施工，流水节拍分别为3、4、3、3和2、5、4、3天，流水步距为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","5",true,"考点:流水步距的确定。（1）求各施工过程流水节拍的累加数列：施工工程甲：3，7，10，13施工过程乙：2，7，11，14（2）错位相减求得差数列：甲与乙：3，5，3，2-14（3）在差数列中取最大值求得流水步距：施工过程甲与乙之间的流水步距：K甲，乙=5。参见教材P31",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]