[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108480,783,1,"单选题","某工程有六个施工段，分为甲、乙、丙、丁四个施工过程。在没有技术间歇和提前插入时间的情况下，组织固定节拍流水施工，若计划工期不超过45天，则各施工过程之间的最大流水步距为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","考点:固定节拍流水施工。因为固定节拍的流水施工流水步距和流水节拍相等，即t＝K，T=（m＋n－1）×K，即（6＋4－1）×K≤45，求得K≤5。流水步距最大为5天。参见教材P27",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]