[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108478":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108478,783,1,"单选题","某分部工程由4个施工过程 （A、 B、 C、 D）组成，分为6个施工段。流水节拍均为3天，无组织间歇时间和工艺间歇时间，但施工过程D需提前2天插入施工，该分部工程的工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","25",true,{"key":23,"text":24,"correct":14},"D","26","考点:固定节拍流水施工。工期＝（4＋6－1）×3－2＝25天。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]