[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108476,783,1,"单选题","组织流水施工时，成倍节拍流水施工的特点（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相同施工过程的流水步距相等，且等于流水节拍",false,{"key":16,"text":17,"correct":18},"B","专业施工队数大于等于施工过程数",true,{"key":20,"text":21,"correct":14},"C","施工段之间没有空闲时间",{"key":23,"text":24,"correct":14},"D","同一施工过程在各个施工段上的流水节拍成倍数关系","考点:成倍节拍流水施工。选项A是固定节拍的流水施工的特点；选项C是加快的成倍节拍流水施工的特点；选项D成倍节拍流水施工在同一施工过程在各个施工段上的流水节拍均相等。参见教材P26～28。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]