[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108475,783,1,"单选题","关于加快的成倍节拍流水施工的特点叙述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不同施工过程的流水节拍相等",false,{"key":16,"text":17,"correct":18},"B","相邻专业工作队的流水步距相等",true,{"key":20,"text":21,"correct":14},"C","专业工作队数等于施工过程数",{"key":23,"text":24,"correct":14},"D","施工段之间可以有空闲时间","考点:成倍节拍流水施工。加快的成倍节拍流水施工的特点如下：（1）同一施工过程在其各个施工段上的流水节拍均相等；不同施工过程的流水节拍不等，但其值为倍数关系；（2）相邻专业工作队的流水步距相等，且等于流水节拍的最大公约数（K）；（3）专业工作队数大于施工过程数，即有的施工过程只成立一个专业工作队，而对于流水节拍大的施工过程，可按其倍数增加相应专业工作队数目；（4）各个专业工作队在施工段上能够连续作业，施工段之间没有空闲时间。参见教材P28",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]