[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108474,783,1,"单选题","某分部工程有4个施工过程，分为3个施工段组织加快的成倍节拍流水施工。已知各施工过程的流水节拍分别为4天、6天、4天和2天，则拟采用的专业工作队应为（ ）个。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","8",true,{"key":23,"text":24,"correct":14},"D","12","考点:成倍节拍流水施工。K=min{4，6，4，2}=2；b1=4\u002F2=2；b2=6\u002F2=3；b3=4\u002F2=2；b4=2\u002F2=1；n，=∑bj=（2+3+2+1）=8（个）。参见教材P29",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]