[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108471,783,1,"单选题","固定节拍流水施工与加快的成倍节拍流水施工相比较，共同的特点是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相邻专业工作队的流水步距相等",true,{"key":16,"text":17,"correct":18},"B","专业工作队数等于施工过程数",false,{"key":20,"text":21,"correct":18},"C","不同施工过程的流水节拍均相等",{"key":23,"text":24,"correct":18},"D","专业工作队数等于施工段数","考点:成倍节拍流水施工。固定节拍流水施工，各施工过程的流水节拍都相等。加快的成倍节拍流水施工，相邻专业工作队的流水步距相等，且等于流水节拍的最大公约数（K）。参见教材P28。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]