[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108470,783,1,"单选题","某建设工程划分为4个施工过程，3个施工段组织加快的成倍节拍流水施工，流水节拍分别为4天、6天、4天和2天，则流水步距为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","6","考点:成倍节拍流水施工。成倍节拍流水施工的流水步距等于流水节拍的最大公约数。4天、6天、4天和2天的最大公约数为2天。参见教材P29。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]