[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108466,783,1,"单选题","考虑建设工程的施工特点、工艺流程、资源利用、平面或空间布置等要求，可采用不同的施工组织方式，其中有利于资源供应的施工组织方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","依次施工和平行施工",false,{"key":16,"text":17,"correct":14},"B","平行施工和流水施工",{"key":19,"text":20,"correct":14},"C","搭接施工和平行施工",{"key":22,"text":23,"correct":24},"D","依次施工和流水施工",true,"考点:流水施工方式。依次施工和流水施工均有利于资源供应的组织。参见教材P21。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]