[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108463,783,1,"单选题","建设工程组织流水施工时，某专业工作队在单位时间内所完成的工程量称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","流水节拍",false,{"key":16,"text":17,"correct":14},"B","流水步距",{"key":19,"text":20,"correct":21},"C","流水强度",true,{"key":23,"text":24,"correct":14},"D","流水节奏","考点:流水施工参数及基本组织方式。在单位时间内所完成的工程量称为流水强度。参见教材P23。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]