[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108460":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108460,783,1,"单选题","每个作业的工人或每台施工机械所需工作面的大小，取决于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","划分施工段的数目",false,{"key":16,"text":17,"correct":14},"B","安全施工的要求",{"key":19,"text":20,"correct":21},"C","单位时间内其完成的工程量和安全施工的要求",true,{"key":23,"text":24,"correct":14},"D","单位时间内其完成的工程量","考点:流水施工参数及基本组织方式。工作面－活动的空间；划分依据：单位时间内完成的工程量、安全施工的要求；影响对象：专业工作队的生产效率。参见教材P23。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]