[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108459":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108459,783,1,"单选题","建设工程组织流水施工时，如果存在间歇时间和提前插入时间，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","间歇时间会使流水施工工期延长，而提前插入时间会使流水施工工期缩短",true,{"key":16,"text":17,"correct":18},"B","间歇时间会使流水施工工期缩短，而提前插入时间会使流水施工工期延长",false,{"key":20,"text":21,"correct":18},"C","无论是间歇时间还是提前插入时间，均会使流水施工工期延长",{"key":23,"text":24,"correct":18},"D","无论是间歇时间还是提前插入时间，均会使流水施工工期缩短","考点:固定节拍流水施工。在计算工期的时候，是加上间歇时间，减去提前插入时间，所以间歇时间会使工期延长，提前插入时间会使工期缩短。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]