[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108450,783,1,"单选题","建设工程组织流水施工时，相邻专业工作队之间的流水步距相等，且施工段之间没有空闲时间的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一般的成倍节拍流水施工和非节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","非节奏流水施工和加快的成倍节拍流水施工",{"key":19,"text":20,"correct":14},"C","一般的成倍节拍流水施工和固定节拍流水施工",{"key":22,"text":23,"correct":24},"D","固定节拍流水施工和加快的成倍节拍流水施工",true,"考点:固定节拍流水施工。固定节拍流水施工相邻施工过程的流水步距相等，施工段之间没有空闲时间。加快的成倍节拍流水施工相邻专业工作队的流水步距相等，施工段之间没有空闲。非节奏流水施工相邻施工过程的流水步距不尽相等，有的施工段之间可能有空闲时间。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]