[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108449,783,1,"单选题","某工程有三个施工过程，划分为5个施工段组织加快的成倍节拍流水施工，各施工过程的流水节拍分别为4天、6天和4天，则参加流水施工的专业工作队总数为（ ）个。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"考点:成倍节拍流水施工。成倍节拍流水施工计算专业工作队数，首先需要求出流水步距，K=最大公约数{4，6，4}=2（天）；专业工作队数=4\u002F2+6\u002F2+4\u002F2=7（个）。参见教材P30。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]