[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108447,783,1,"单选题","某分部工程有3个施工过程，各分为4个流水节拍相等的施工段，各施工过程的流水节拍分别为6、4、4天。如果组织加快的成倍节拍流水施工，则专业工作队数和流水施工工期分别为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3个和20天",false,{"key":16,"text":17,"correct":14},"B","4个和25天",{"key":19,"text":20,"correct":14},"C","5个和24天",{"key":22,"text":23,"correct":24},"D","7个和20天",true,"考点:成倍节拍流水施工。6、4、4天的最大公约数为2天。专业工作队数=6\u002F2+4\u002F2+4\u002F2=7个。流水施工工期=（7-1+4）×2=20天。参见教材P29。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]