[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108446,783,1,"单选题","某基础工程划分4个施工过程（挖基槽、作垫层、混凝土浇筑、回填土）在5个施工段组织固定节拍流水施工，流水节拍为3天，要求混凝土浇筑3天后才能进行回填土，该工程的流水工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","39",false,{"key":16,"text":17,"correct":14},"B","29",{"key":19,"text":20,"correct":21},"C","27",true,{"key":23,"text":24,"correct":14},"D","14","考点:固定节拍流水施工。流水施工工期=（5+4－1）×3+3=27天。参见教材P27。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]