[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108445,783,1,"单选题","某分部工程有3个施工过程，分为4个施工段组织加快的成倍节拍流水施工，各施工过程流水节拍分别是9天、6天、9天，则该分部工程的流水施工工期是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24",false,{"key":16,"text":17,"correct":18},"B","33",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","54","考点:成倍节拍流水施工。施工过程数目n=3，施工段数目m=4，流水步距等于流水节拍的最大公约数，K=min{6，6，9}=3，专业工作队数=（9\u002F3）+（6\u002F3）+（9\u002F3）=8（个），流水施工工期=（4+8-1）×3=33（天）。参见教材P29。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]