[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108443,783,1,"单选题","建设工程采用平行施工组织方式的特点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","能够均匀使用施工资源",false,{"key":16,"text":17,"correct":14},"B","单位时间内投入的资源量较少",{"key":19,"text":20,"correct":14},"C","专业工作队能够连续施工",{"key":22,"text":23,"correct":24},"D","能够充分利用工作面进行施工",true,"考点:流水施工方式。平行施工特点：（1）充分利用工作面进行施工，工期短；（2）如果每一个施工对象均按专业成立工作队，劳动力及施工机具等资源无法均衡使用；（3）如果由一个工作队完成一个施工对象的全部施工任务，则不能实现专业化施工，不利于提高劳动生产率；（4）单位时间内投入的劳动力、施工机具、材料等资源量成倍地增加，不利于资源供应的组织；（5）施工现场的组织管理比较复杂。参见教材P21",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]