[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108441,783,1,"单选题","流水施工空间参数中，工作面的大小表明（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工速度的快慢",false,{"key":16,"text":17,"correct":14},"B","能划分施工段的多少",{"key":19,"text":20,"correct":14},"C","能完成工程量的多少",{"key":22,"text":23,"correct":24},"D","能安排施工人数或机械台数的多少",true,"考点:流水施工参数。工作面的大小，能反映安排施工人数或机械台数的多少。参见教材P23",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]