[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108440":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108440,783,1,"单选题","下列计算方法中，不能用来计算流水节拍的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","倒排进度法",false,{"key":16,"text":17,"correct":18},"B","计量计价法",true,{"key":20,"text":21,"correct":14},"C","经验估算法",{"key":23,"text":24,"correct":14},"D","定额计算法","考点:流水施工参数。流水节拍可分别按下列方法确定：工期反算法（倒排进度法）、经验估算法、定额计算法。参见教材P25",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]