[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108438,783,1,"单选题","在组织建设工程流水施工时，某个专业工作队在一个施工段上的施工时间称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流水节拍",true,{"key":16,"text":17,"correct":18},"B","流水工期",false,{"key":20,"text":21,"correct":18},"C","流水步距",{"key":23,"text":24,"correct":18},"D","流水强度","考点:流水施工参数。流水节拍是指在组织流水施工时，某个专业工作队在一个施工段上的施工时间。参见教材P24。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]