[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108437":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108437,783,1,"单选题","流水施工参数中，流水步距的数目取决于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作面",false,{"key":16,"text":17,"correct":14},"B","施工段数",{"key":19,"text":20,"correct":14},"C","流水节拍",{"key":22,"text":23,"correct":24},"D","参加流水的施工过程数",true,"考点:流水施工参数。流水步距的数目取决于参加流水的施工过程数。如果施工过程数位n个，则流水步距的总数为n-1。参见教材P25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]