[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108435,783,1,"单选题","组织建设工程流水施工时，根据施工组织及计划安排需要而将计划任务划分成的子项是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程",true,{"key":16,"text":17,"correct":18},"B","流水步距",false,{"key":20,"text":21,"correct":18},"C","工作面",{"key":23,"text":24,"correct":18},"D","施工段","考点:流水施工参数及基本组织方式。组织建设工程流水施工时，根据施工组织及计划安排需要而将计划任务划分成的子项称为施工过程。参见教材P23。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]