[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108432,783,1,"单选题","流水步距的数目取决于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作面",false,{"key":16,"text":17,"correct":18},"B","参加流水的施工过程数",true,{"key":20,"text":21,"correct":14},"C","流水节拍",{"key":23,"text":24,"correct":14},"D","施工段数","考点:流水施工参数及基本组织方式。流水步距的数目取决于参加流水的施工过程数。参见教材P25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]