[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108429":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108429,783,1,"单选题","在建设工程监理工作中，建立工程进度报告制度及进度信息沟通网络属于监理工程师控制进度的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经济措施",false,{"key":16,"text":17,"correct":14},"B","合同措施",{"key":19,"text":20,"correct":21},"C","组织措施",true,{"key":23,"text":24,"correct":14},"D","技术措施","考点:进度控制的措施和主要任务。组织措施包括：建立进度控制目标体系，明确建设工程现场监理组织机构中进度控制人员及其职责分工；建立工程进度报告制度及进度信息沟通网络；建立进度计划审核制度和进度计划实施中的检查分析制度；建立进度协调会议制度，包括协调会议举行的时间、地点，协调会议的参加人员等；建立图纸审查、工程变更和设计变更管理制度。参见教材P2。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]