[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108426,783,1,"单选题","下列建设工程进度控制因素中，属于业主因素的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","地下埋藏文物的保护.处理",false,{"key":16,"text":17,"correct":14},"B","合同签订的遗漏条款.表达失当",{"key":19,"text":20,"correct":21},"C","施工现场不能及时提供",true,{"key":23,"text":24,"correct":14},"D","特殊材料及新材料的不合理使用","考点:影响进度的因素分析。业主因素如业主使用要求改变而进行设计变更；应提供的施工场地条件不能及时提供或所提供的场地不能满足工程正常需要；不能及时向施工承包单位或材料供应商付款等。参见教材P2。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]