[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108425,783,1,"单选题","在工程建设过程中，由于领导不力，指挥失当，使参加工程建设的各个单位配合上发生矛盾影响施工进度，属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主因素",false,{"key":16,"text":17,"correct":18},"B","组织管理因素",true,{"key":20,"text":21,"correct":14},"C","施工技术因素",{"key":23,"text":24,"correct":14},"D","社会环境因素","考点:影响进度的因素分析。组织管理因素：向有关部门提出各种申请审批手续的延误；合同签订时遗漏条款、表达失当；计划安排不周密，组织协调不力，导致停工待料、相关作业脱节；领导不力，指挥失当，使参加工程建设的各个单位、各个专业、各个施工过程之间交接、配合上发生矛盾等。参见教材P2。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]