[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108424,783,1,"单选题","采取CM承发包模式，属于控制建设工程进度的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","组织措施","考点:进度控制的措施和主要任务。进度控制的合同措施主要包括：（1）推行CM承发包模式，对建设工程实行分段设计、分段发包和分段施工；（2）加强合同管理，协调合同工期与进度计划之间的关系，保证合同中进度目标的实现；（3）严格控制合同变更，对各方提出的工程变更和设计变更，监理工程师应严格审查后再补入合同文件之中；（4）加强风险管理，在合同中应充分考虑风险因素及其对进度的影响，以及相应的处理方法；（5）加强索赔管理，公正地处理索赔。参见教材P3。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]