[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108423":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108423,783,1,"单选题","编制工程项目总进度计划是（ ）进度控制的主要任务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计准备阶段",true,{"key":16,"text":17,"correct":18},"B","设计阶段",false,{"key":20,"text":21,"correct":18},"C","施工图设计阶段",{"key":23,"text":24,"correct":18},"D","施工阶段","考点:进度控制的措施和主要任务。设计准备阶段进度控制的任务：（1）收集有关工期的信息，进行工期目标和进度控制决策；（2）编制工程项目总进度计划；（3）编制设计准备阶段详细工作计划，并控制其执行；（4）进行环境及施工现场条件的调查和分析。参见教材P3。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]