[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108422":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108422,783,1,"单选题","在进行建设项目总进度目标控制前，建设单位对项目总进度管理的首要任务是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","收集和整理比较详细的设计资料",false,{"key":16,"text":17,"correct":14},"B","比较和分析各项技术方案的合理性",{"key":19,"text":20,"correct":14},"C","提出和改进设计.施工的进度控制措施",{"key":22,"text":23,"correct":24},"D","分析和论证进度目标实现的可能性",true,"考点:建设项目总进度目标的论证。在进行建设项目总进度目标控制前，首先应分析和论证目标实现的可能性。参见教材P4",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]