[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108420":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108420,783,1,"单选题","项目的工作编码指的是每一个工作项的编码，编码时应考虑的因素不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划层",false,{"key":16,"text":17,"correct":18},"B","投资规模",true,{"key":20,"text":21,"correct":14},"C","计划对象",{"key":23,"text":24,"correct":14},"D","工作内容","考点:建设项目总进度目标的论证。项目的工作编码指的是每一个工作项的编码，编码时应考虑的因素：（1）对不同计划层的标识；（2）对不同计划对象的标识；（3）对不同工作的标识。参见教材P5",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]