[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108419,783,1,"单选题","下列选项中不属于建设项目总进度目标论证的工作步骤中调查研究和收集资料包括的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","了解和收集设计阶段有关项目进度目标确定的情况和资料",true,{"key":16,"text":17,"correct":18},"B","收集与进度有关的该项目组织.管理.经济和技术资料",false,{"key":20,"text":21,"correct":18},"C","了解和调查该项目的总体部署",{"key":23,"text":24,"correct":18},"D","了解和调查该项目实施的主客观条件","考点:建设项目总进度目标的论证。调查研究和收集资料包括如下工作：了解和收集项目决策阶段有关项目进度目标确定的情况和资料；收集与进度有关的该项目组织、管理、经济和技术资料；收集类似项目的进度资料；了解和调查该项目的总体部署；了解和调查该项目实施的主客观条件等。参见教材P5",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]